FY 21-25 CIP

thru FY 21 FY 25

Capital Improvement Plan City of Spencer, Iowa

Department Sanitary Sewer

Contact Public Works Director

Type Maintenance

Project #

18-SEW-002

Useful Life 20 Years

Project Name COUNTRY CLUB LIFT STATION REHABILITATION

Category Sewer Improvements

Priority 2 - Essential

Total Project Cost: $57,000

Description The proposed project consists of 2 phases. Phase 1 would move the control panel above ground and replace of the pumps with a dry pit submersible pump (15 HP). Phase 2 consists of the rehabilitation of the wet well.

Justification At the time of replacement, the controls would be 48 years old and in need of replacement. Technology has changed since the original controls were installed.

Over the years, the wet well has deteriorated to the point of needing repair. At the time of rehabilitation, the wet well will be 49 years old.

Also, the project would allow the lift station to operate during a flooding event.

Prior

Expenditures

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Construction/Maintenance

21,000

21,000

36,000

21,000

21,000

Total

Total

Prior

Funding Sources

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Sewer Reserve

21,000

21,000

36,000

21,000

21,000

Total

Total

Made with FlippingBook flipbook maker