FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Sanitary Sewer
Contact Public Works Director
Type Maintenance
Project #
15-SEW-001
Useful Life 20 Years
Project Name W. 4TH STREET LIFT STATION REHABILITATION
Category Sewer Improvements
Priority 2 - Essential
Total Project Cost: $52,087
Description The proposed project will consist of three components. The first is updating the control panel at the W. 4th Street lift station. The control panel tells the pumps when to turn on and off and alerts staff if there are issues with the station. This portion of the project will be completed in 2015. The second component of the project is replacing the valves at the lift station. The valves control the flow of sewage into and out of the station. This portion of the project will be completed in 2015. The third component of the project is to repair the outside of the concrete wet well and pump repairs. This portion of the project will be completed in 2021. Justification At the time of replacement, the current panel will be 42 years old. Over that time, technology has changed and the current panel is out of date.
At the time of replacement, the valves will also be 42 years old and in need of replacement. By repairing the outside of the wet well, the life expectancy of the well will be extended. This project is being recommended by our Treatment Plant Operators Veolia.
Prior
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Construction/Maintenance
29,000
29,000
23,087
29,000
29,000
Total
Total
Prior
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Sewer Reserve
29,000
29,000
23,087
29,000
29,000
Total
Total