Capital Improvement Plan City of Spencer, Iowa
Department Sanitary Sewer
Contact Public Works Director
Type Maintenance
Project #
18-SEW-002
Useful Life 20 Years
Project Name COUNTRY CLUB LIFT STATION REHABILITATION
Category Sewer Improvements
Priority 2 - Essential
Total Project Cost: $57,000
Description The proposed project consists of 2 phases. Phase 1 would move the control panel above ground and replace of the pumps with a dry pit submersible pump (15 HP). Phase 2 consists of the rehabilitation of the wet well.
Justification At the time of replacement, the controls would be 48 years old and in need of replacement. Technology has changed since the original controls were installed.
Over the years, the wet well has deteriorated to the point of needing repair. At the time of rehabilitation, the wet well will be 49 years old.
Also, the project would allow the lift station to operate during a flooding event.
Prior
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Construction/Maintenance
21,000
21,000
36,000
21,000
21,000
Total
Total
Prior
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Sewer Reserve
21,000
21,000
36,000
21,000
21,000