FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Landfill
Contact Public Works Director
Type Improvement
Project #
24-LF-001
Useful Life 30 Years
Project Name Driveway Pavement
Category Landfill Improvements
Priority 4 - Desirable
Total Project Cost: $122,000
Description The proposed project would pave the driveway and employee parking areas at the landfill. This would be an extension of the paving project at the landfill in FY 2020.
Justification The project would help improve operations.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Planning/Design
24,186
24,186
Construction/Maintenance
97,814
97,814
122,000
122,000
Total
Prior
122,000
Total