FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Landfill
Contact Public Works Director
Type Maintenance
Project #
22-LF-001
Useful Life 10 Years
Project Name AL-JON REFURBISHMENT
Category Equipment: General
Priority 3 - Important
Total Project Cost: $420,000
Description The proposed project will be sent back to the factory for a complete refurbishment and rebuild of all components, wiring and a new paint job.
Justification This preventative work should help extend the overall life of the machine.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Equipment
420,000
420,000
420,000
420,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Landfill Reserve
420,000
420,000
420,000
420,000
Total