FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Landfill
Contact Public Works Director
Type Improvement
Project #
21-LF-005
Useful Life 25 Years
Project Name Scale Replacement
Category Equipment: General
Priority 3 - Important
Total Project Cost: $165,000
Description The proposed project would replace the scale at the landfill.
Justification The existing scale was used when we purchased the landfill and has some maintenance issues.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Equipment
165,000
165,000
165,000
165,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Landfill Reserve
165,000
165,000
165,000
165,000
Total