FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Landfill
Contact Public Works Director
Type Improvement
Project #
21-LF-001
Useful Life 50 Years
Project Name SHOP ADDITION
Category Buildings
Priority 2 - Essential
Total Project Cost: $240,000
Description The proposed project would consist of the construction of an addition to the existing shop building.
Justification The purpose of the project tis to improve shop efficiency for projects. At the time the current building was built, the City was under tight budget constraints and built a building that the budget would allow.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Planning/Design
20,000
20,000
Construction/Maintenance
220,000
220,000
240,000
240,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Landfill Reserve
240,000
240,000
240,000
240,000
Total