FY 21-25 CIP

thru FY 21 FY 25

Capital Improvement Plan City of Spencer, Iowa

Department Airport

Contact Public Works Director

Type Maintenance

Project #

22-AIR-002

Useful Life 20 Years

Project Name REHAB HANGAR FIRE WALL

Category Buildings

Priority 5 - On-Going

Total Project Cost: $65,000

Description The proposed project would construct a fire separation wall in the conventional hangar complex.

Justification To increase fire protection of the multiple users and spaces within the large hangar complex at the airport.

Expenditures

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Planning/Design

10,834

10,834

Construction/Maintenance

54,166

54,166

65,000

65,000

Total

Funding Sources

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Airport Reserve

16,250

16,250

Grant: State Airport

48,750

48,750

65,000

65,000

Total

Made with FlippingBook flipbook maker