FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Airport
Contact Public Works Director
Type Maintenance
Project #
22-AIR-002
Useful Life 20 Years
Project Name REHAB HANGAR FIRE WALL
Category Buildings
Priority 5 - On-Going
Total Project Cost: $65,000
Description The proposed project would construct a fire separation wall in the conventional hangar complex.
Justification To increase fire protection of the multiple users and spaces within the large hangar complex at the airport.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Planning/Design
10,834
10,834
Construction/Maintenance
54,166
54,166
65,000
65,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Airport Reserve
16,250
16,250
Grant: State Airport
48,750
48,750
65,000
65,000
Total