FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Airport
Contact Public Works Director
Type Maintenance
Project #
21-AIR-004
Useful Life 15 Years
Project Name Ditch Cleaning
Category Airport Improvements
Priority 2 - Essential
Total Project Cost: $50,000
Description The proposed project would hire a contractor to clean the drainage ditches along the western edge of the airport.
Justification Surface water is backing up and not draining as designed.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Construction/Maintenance
50,000
50,000
50,000
50,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Airport Reserve
50,000
50,000
50,000
50,000
Total