FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department WTP
Contact Public Works Director
Type Maintenance
Project #
23-WTP-001
Useful Life 25 Years
Project Name RBC COVER REPLACEMENT
Category WTP Improvements
Priority 2 - Essential
Total Project Cost: $50,000
Description The proposed project will replace five RBC covers on the units at the wastewater treatment plant.
Justification The project is part of routine maintenance on the units and will assist in extending the life of each unit.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Equipment
50,000
50,000
50,000
50,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
WTP Reserve
50,000
50,000
50,000
50,000
Total
Made with FlippingBook flipbook maker