FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Streets - Equipment
Contact Public Works Director
Type Equipment
Project #
25-STEQ-001
Useful Life 15 Years
Project Name 3/4 ton Pick Up
Category Equipment: Vehicles
Priority 1 - Imperative
Total Project Cost: $36,000
Description The proposed project would purchase a 3/4 ton chassis cab. A new flatbed would be installed on the chassis.
Justification This purchase will replace a 2004 truck that will be 20 years old at the time of replacement.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Vehicles
36,000
36,000
36,000
36,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
PW Equipment Reserve
36,000
36,000
36,000
36,000
Total