FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Streets - Equipment
Contact Public Works Director
Type Equipment
Project #
21-STEQ-002
Useful Life 15 Years
Project Name ARM MOWER REPLACEMENT
Category Equipment: Miscellaneous
Priority 3 - Important
Total Project Cost: $53,000
Description The proposed project will replace the current boom mower with a new piece of equipment. This purchase will coincide with the purchase of a new tractor.
Justification The current unit was purchased in 199 and will be in need of replacement.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Equipment
53,000
53,000
53,000
53,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
PW Equipment Reserve
53,000
53,000
53,000
53,000
Total