Capital Improvement Plan City of Spencer, Iowa
Department Streets
Contact Public Works Director
Type Improvement
Project #
25-STR-001
Useful Life 40 Years
Project Name 2025 RECONSTRUCTION
Category Street Reconstruction
Priority 1 - Imperative
Total Project Cost: $455,000
Description The proposed project would consist of the reconstruction f 10th Ave E from East 19th Street north 1,450 feet.
Justification The street has seen an increase in heavy truck traffic as a result of the beltway projects. The surface is beginning to fail.
The City will make an application for TEA 21 funding prior to the project.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Planning/Design
80,000
80,000
Construction/Maintenance
375,000
375,000
455,000
455,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Special Assessments
176,000
176,000
Street Improvement Reserve
279,000
279,000
455,000
455,000
Total