FY 21-25 CIP

thru FY 21 FY 25

Capital Improvement Plan City of Spencer, Iowa

Department Streets

Contact Public Works Director

Type Improvement

Project #

21-STR-004

Useful Life 50 Years

Project Name W 4TH ST STORM SEWER EXTENSION

Category Street Construction

Priority 2 - Essential

Total Project Cost: $380,000

Description The proposed project would extend storm sewer, prior to the FY22 HMA overlay. The storm sewer would be extended from the south side of W 4th Street at 2nd Ave W to 1st Ave W on the north side of W 4th Street. This will also include sidewalk improvements at 1st Ave.

Justification This work will be done prior to the overlay of 4th Ave to prevent future disruption to a newly overlayed street.

Expenditures

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Planning/Design

49,000

49,000

Construction/Maintenance

331,000

331,000

380,000

380,000

Total

Funding Sources

Total

FY 21

FY 22

FY 23

FY 24

FY 25

Sewer Reserve

19,520

19,520

Storm Sewer Reserve

171,060

171,060

Street Improvement Reserve

189,420

189,420

380,000

380,000

Total

Made with FlippingBook flipbook maker