FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Streets
Contact Public Works Director
Type Improvement
Project #
21-STR-004
Useful Life 50 Years
Project Name W 4TH ST STORM SEWER EXTENSION
Category Street Construction
Priority 2 - Essential
Total Project Cost: $380,000
Description The proposed project would extend storm sewer, prior to the FY22 HMA overlay. The storm sewer would be extended from the south side of W 4th Street at 2nd Ave W to 1st Ave W on the north side of W 4th Street. This will also include sidewalk improvements at 1st Ave.
Justification This work will be done prior to the overlay of 4th Ave to prevent future disruption to a newly overlayed street.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Planning/Design
49,000
49,000
Construction/Maintenance
331,000
331,000
380,000
380,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Sewer Reserve
19,520
19,520
Storm Sewer Reserve
171,060
171,060
Street Improvement Reserve
189,420
189,420
380,000
380,000
Total