FY 21-25 CIP
thru FY 21 FY 25
Capital Improvement Plan City of Spencer, Iowa
Department Solid Waste
Contact Public Works Director
Type Maintenance
Project #
21-SW-001
Useful Life 6 Years
Project Name Loader Tire Replacement
Category Equipment: General
Priority 1 - Imperative
Total Project Cost: $25,000
Description The proposed project would purchase new tires on the wheel loader that is used to load transfer trailers. These tires are foam filled to prevent flats.
Justification The current tires are worn out.
Expenditures
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Equipment
25,000
25,000
25,000
25,000
Total
Funding Sources
Total
FY 21
FY 22
FY 23
FY 24
FY 25
Solid Waste Reserve
25,000
25,000
25,000
25,000
Total