FY 2020-2024 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 20 FY 24
Contact Public Works Director Department Safe Routes to School
Type Improvement
23-SRTS-001
Project #
Useful Life 30 Years
Project Name 5th AVE E SIDEWALK
Priority 3 - Important Category Sidewalks
Description The proposed project will complete the sidewalk system on 5th Avenue East from East 16th Street to East 19th Street. The project will also include ADA compliant ramps Total Project Cost: $75,000
Justification The project will complete the sidewalk system that connects to Fairview School.
Expenditures Planning/Design
Total
FY 20
FY 21
FY 22
FY 23
FY 24
7,500
7,500
67,500 75,000
67,500 75,000
Construction/Maintenance
Total
Funding Sources
Total
FY 20
FY 21
FY 22
FY 23
FY 24
75,000 75,000
75,000 75,000
SRTS Reserve
Total
Made with FlippingBook - Online catalogs