FY 2020-2024 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 20 FY 24
Contact Public Works Director Department Safe Routes to School
Type Improvement
22-SRTS-001
Project #
Useful Life 30 Years
Project Name ADA RAMP UPGRADES
Priority 2 - Essential Category Sidewalks
Total Project Cost: $80,000
Description The proposed project would construct 23 ADA compliant sidewalk ramps in the following intersections:
7th Avenue W & W 9th Street 9th Avenue W & W 9th Street 11th Avenue W & W 9th Street 11th Avenue W & W 10th Street 11th Avenue W & W 11th Street West side of 11th Avenue W at the YMCA
Justification The purpose of the project is to bring these non-compliant ramps up to compliance and the location of the schools and YMCA makes this a great opportunity.
Expenditures
FY 20
FY 21
FY 22
FY 23
FY 24
Total
30,000 30,000
50,000 50,000
80,000 80,000
Construction/Maintenance
Total
Funding Sources
FY 20
FY 21
FY 22
FY 23
FY 24
Total
30,000 30,000
50,000 50,000
80,000 80,000
SRTS Reserve
Total