FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
FY 19 FY 23 thru
PROJECTS & FUNDING SOURCES BY DEPARTMENT
Department
Project # Priority
Total
FY 19 FY 20 FY 21 FY 22 FY 23
Landfill FENCING
12-LF-001 14-LF-001 19-LF-001 19-LF-002 19-LF-003 20-LF-001 20-LF-002 21-LF-001 21-LF-002
4 1 1 1 2 1 2 1 2
60,000 730,000
60,000 730,000 150,000 100,000 125,000 300,000 30,000 150,000 88,000
LANDFILL CELL DEVELOPMENT EQUIPMENT STORAGE BUILDING
150,000 100,000 125,000
SCALE CONCRETE
SEMI TRACTOR
TRACK LOADER REPLACEMENT
300,000 30,000
VEHICLE REPLACEMENT
SHOP ADDITION
150,000 88,000
LEACHATE TANKER
375,000
330,000 1,028,000
1,733,000
Landfill Total
730,000 298,000
730,000
Landfill Cell Constr Reserve
375,000
330,000
1,003,000
Landfill Reserve
375,000
330,000 1,028,000
1,733,000
Landfill Total
375,000
330,000 1,028,000
1,733,000
Grand Total
Made with FlippingBook - professional solution for displaying marketing and sales documents online