Useful Life 20 Years Category Buildings
Project Name PORTABLE HOOP STORAGE BUILDING
Priority 4 - Desirable
Description The proposed project would construct a hoop building on steel frame for the storage of the Al-Jon close to the working face of the landfill. Total Project Cost: $25,000
Justification This would keep the unit out of the elements during off hours, and help improve operator safety.
Expenditures
Total
FY 20
FY 21
FY 22
FY 23
FY 24
25,000 25,000
25,000 25,000
Building
Total
Funding Sources
Total
FY 20
FY 21
FY 22
FY 23
FY 24
25,000 25,000
25,000 25,000
Landfill Reserve
Total