FY 2020-2024 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 20 FY 24
Department Fire
Contact Fire Chief
Type Equipment
13-FIRE-001
Project #
Useful Life 10 Years
Project Name BUNKER GEAR REPLACEMENT
Category Equipment: Miscellaneous
Priority 5 - On-Going
Total Project Cost: $109,419
Description The proposed project consists of replacing the department's bunker gear in a timely manner.
Justification As the Department engages in activities, bunker gear can wear out due to use. The project ensures that all bunker gear used by the Department is in good working order.
Prior
Expenditures
Total
FY 20
FY 21
FY 22
FY 23
FY 24
20,000 20,000
20,000 20,000
40,000 40,000
69,419
Equipment
Total
Total
Prior
Funding Sources
Total
FY 20
FY 21
FY 22
FY 23
FY 24
20,000 20,000
20,000 20,000
40,000 40,000
69,419
Fire Reserve
Total
Total
Made with FlippingBook - Online catalogs