FY 2020-2024 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 20 FY 24
Department Streets - Equipment
Contact Public Works Director
Type Equipment
13-STEQ-001
Project #
Useful Life 15 Years
Project Name PLOW TRUCK / DUMP BODY
Category Equipment: Vehicles
Priority 5 - On-Going
Description The proposed project will replace the current 2000 International plow truck with a new single axle plow truck. Included with the purchase will be a new dump body, plow and sander unit. Total Project Cost: $650,412
Justification The 2016 project will replace a 2000 International plow truck, which at the time of replacement, will be 16 years old. The 2018 project will replace a 2000 International plow truck, which at the time of replacement, will be 18 years old.
Prior
Expenditures
Total
FY 20
FY 21
FY 22
FY 23
FY 24
172,500 172,500
172,500 172,500
477,912
Vehicles
Total
Total
Prior
Funding Sources PW Equipment Reserve
Total
FY 20
FY 21
FY 22
FY 23
FY 24
172,500 172,500
172,500 172,500
477,912
Total
Total