FY 2020-2024 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 20 FY 24
Department Streets
Contact Public Works Director
Type Maintenance
22-STR-001
Project #
Useful Life 20 Years
Project Name 4TH STREET HMA OVERLAY
Priority 2 - Essential Category Street Paving
Description The proposed project would consist of a mill and overlay on 4th Street beginning at 5th Ave East and continuing west until the 900 block of W 4th Street. Resurfacing varies from 24' to 66' in width and the total length is 5,680 feet. Total Project Cost: $1,215,000
Justification The overall condition of the road is in poor condition, however sections of this street have been replaced in the past few years with other construction projects. 4th Street is a major thoroughfare through the community and receives a high volume of traffic.
Expenditures Planning/Design
Total
FY 20
FY 21
FY 22
FY 23
FY 24
95,000
95,000
1,120,000 1,215,000
1,120,000 1,215,000
Construction/Maintenance
Total
Funding Sources
Total
FY 20
FY 21
FY 22 400,000 120,000 320,000 375,000 1,215,000
FY 23
FY 24
400,000 120,000 320,000 375,000
Grant: MAP-21
Road Use Tax (RUT) Storm Sewer Reserve
Street Improvement Reserve
1,215,000
Total