FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 19 FY 23
Department Landfill
Contact Public Works Director
Type Improvement
19-LF-002
Project #
Useful Life 30 Years
Project Name SCALE CONCRETE
Category Landfill Improvements
Priority 2 - Essential
Description The proposed project would install concrete at the driveway entrance as well as a system to remove dirt from vehicle tires as they leave the facility. Total Project Cost: $100,000
Justification The purpose of the project is to reduce the material that is deposited onto the state highway.
Expenditures
Total
FY 19
FY 20
FY 21
FY 22
FY 23
100,000 100,000
100,000 100,000
Construction/Maintenance
Total
Funding Sources
Total
FY 19
FY 20
FY 21
FY 22
FY 23
100,000 100,000
100,000 100,000
Landfill Reserve
Total
Made with FlippingBook - professional solution for displaying marketing and sales documents online