FY 2019-2023 Capital Improvement Plan

Capital Improvement Plan City of Spencer, Iowa

thru FY 19 FY 23

Department Fire

Contact Fire Chief

Type Equipment

14-FIRE-001

Project #

Useful Life 12 Years

Project Name HOSE REPLACEMENT

Category Equipment: Miscellaneous

Priority 5 - On-Going

Total Project Cost: $29,557

Description The proposed project will consist of replacing sections of 5" hose. As hose wears out, sections will be replaced.

Justification Sections of 5" hose that fail to meet a service test will be replaced. This will ensure that the likeability of a hose failure during a fire is reduced.

Prior

Expenditures

Total

FY 19

FY 20

FY 21

FY 22

FY 23

7,500 7,500

7,500 7,500

15,000 15,000

14,557

Equipment

Total

Total

Prior

Funding Sources

Total

FY 19

FY 20

FY 21

FY 22

FY 23

7,500 7,500

7,500 7,500

15,000 15,000

14,557

Fire Reserve

Total

Total