FY 2019-2023 Capital Improvement Plan

Capital Improvement Plan City of Spencer, Iowa

thru FY 19 FY 23

Department WTP

Contact Public Works Director

Type Maintenance

22-WTP-002

Project #

Useful Life 30 Years

Project Name DRIVEWAY REPLACEMENT

Category WTP Improvements

Priority 3 - Important

Description The proposed project would replace the current concrete driveway at the wastewater treatment plant facility and pave the existing dirt road to the equalization pond. Total Project Cost: $370,000

Justification The concrete will be approximately 43 years old at the time of replacement and has deteriorated due to heavy truck traffic.

Expenditures Planning/Design

Total

FY 19

FY 20

FY 21

FY 22 20,000 350,000 370,000

FY 23

20,000 350,000 370,000

Construction/Maintenance

Total

Funding Sources

Total

FY 19

FY 20

FY 21

FY 22 370,000 370,000

FY 23

370,000 370,000

WTP Reserve

Total