The proposed project would replace the current concrete driveway at the wastewater treatment plant facility and pave the existing dirt road to the equalization pond. 22-WTP-002 DRIVEWAY REPLACEMENT The concrete will be approximately 43 years old at the time of replacement and has deteriorated due to heavy truck traffic.
Description:
Justification: Budget Impact:
Maintenance costs should go down with new pavement at the facility.
The proposed project will replace five RBC covers on the units at the wastewater treatment plant. 23-WTP-001 RBC COVER REPLACEMENT The project is part of routine maintenance on the units and will assist in extending the life of each unit.
Description: Justification: Budget Impact: