FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 19 FY 23
Department Streets - Equipment
Contact Public Works Director
Type Equipment
21-STEQ-002
Project #
Useful Life 15 Years
Project Name ARM MOWER REPLACEMENT
Category Equipment: Miscellaneous
Priority 3 - Important
Description The proposed project will replace the current boom mower with a new piece of equipment. This purchase will coincide with the purchase of a new tractor. Total Project Cost: $50,000
Justification The current unit was purchased in 199 and will be in need of replacement.
Expenditures
Total
FY 19
FY 20
FY 21
FY 22
FY 23
50,000 50,000
50,000 50,000
Equipment
Total
Funding Sources PW Equipment Reserve
Total
FY 19
FY 20
FY 21
FY 22
FY 23
50,000 50,000
50,000 50,000
Total