FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 19 FY 23
Department Streets - Equipment
Contact Public Works Director
Type Equipment
19-STEQ-006
Project #
Useful Life 10 Years
Project Name GASBOY TANK MONITOR UPGRADE
Priority 2 - Essential Category Technology
Total Project Cost: $25,000
Description The proposed project will upgrade the fuel tank monitoring system used at the central fueling facility.
Justification The new upgrades will enable a better interface with current system and allow for better monitoring of the fuel that is being used.
Expenditures
Total
FY 19
FY 20
FY 21
FY 22
FY 23
25,000 25,000
25,000 25,000
Equipment
Total
Funding Sources
Total
FY 19
FY 20
FY 21
FY 22
FY 23
25,000 25,000
25,000 25,000
Fuel Equipment Reserve
Total
Made with FlippingBook - professional solution for displaying marketing and sales documents online