FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
thru FY 19 FY 23
Department Streets
Contact Public Works Director
Type Maintenance
21-STR-001
Project #
Useful Life 20 Years
Project Name 2021 RECONSTRUCTION
Category Street Reconstruction
Priority 2 - Essential
Total Project Cost: $558,360
Description The proposed project consists of the mill and overlay of Woodland Ave and Fairway Street.
Justification Both of these streets are in poor condition and are n need of an overlay to prolong the life expectancy.
Expenditures Planning/Design
Total
FY 19
FY 20
FY 21 93,060 465,300 558,360
FY 22
FY 23
93,060 465,300 558,360
Construction/Maintenance
Total
Funding Sources Special Assessments Storm Sewer Reserve
Total
FY 19
FY 20
FY 21 180,480 166,920 210,960 558,360
FY 22
FY 23
180,480 166,920 210,960 558,360
Street Improvement Reserve
Total
Made with FlippingBook - professional solution for displaying marketing and sales documents online