FY 2019-2023 Capital Improvement Plan

Capital Improvement Plan City of Spencer, Iowa

thru FY 19 FY 23

Contact Public Works Director Department Safe Routes to School

Type Equipment

19-SRTS-003

Project #

Useful Life 15 Years

Project Name PEDESTRIAN CROSSING IMPROVEMENTS

Priority 2 - Essential Category Sidewalks

Description The proposed project will consist of the purchase and installation of new pedestrian cross walk signal equipment at E 18th Street and 5th Ave E crossing. Total Project Cost: $5,000

Justification The current equipment is out of date and needs to be replaced for reliable operation.

Expenditures

Total

FY 19

FY 20

FY 21

FY 22

FY 23

5,000 5,000

5,000 5,000

Equipment

Total

Funding Sources

Total

FY 19

FY 20

FY 21

FY 22

FY 23

5,000 5,000

5,000 5,000

SRTS/Sidewalk Reserve

Total

Made with FlippingBook - professional solution for displaying marketing and sales documents online