FY 2019-2023 Capital Improvement Plan
Capital Improvement Plan City of Spencer, Iowa
PROJECTS BY CATEGORY AND DEPARTMENT FY 19 FY 23 thru
Department Category
Total
Future
FY 19
FY 20 FY 21
FY 22
FY 23
Sanitary Sewer Equipment: General
UTILITY TRAILER
1,800 1,800
1,800 1,800
Sub-Total
Equipment: Vehicles VEHICLE REPLACEMENT
37,500 37,500
37,500 37,500
Sub-Total
Sewer Improvements MANHOLE REHABILITATION SEWER LINING PROJECT
25,000
25,000 150,000
25,000
25,000
30,000
130,000 150,000 28,000 28,000 28,000 28,000 250,000 50,000 692,000 731,300
W. 4TH STREET LIFT STATION REHABILITATION
28,000 18,000 18,000 18,000 50,000 50,000 207,000 208,800
NORTH LIFT STATION REHABILITATION
10,000 10,000 10,000 50,000
COUNTRY CLUB LIFT STATION REHABILITATION CORN BELT LIFT STATION REHABILITATION
INTAKE CATCH BASIN REHABILITATION WEST 4TH ST MAIN MAINTENANCE
50,000
50,000
50,000
225,000 225,000
105,000 142,500
75,000 75,000
80,000 80,000
Sub-Total
Department Total:
208,800
225,000
142,500
75,000
80,000
731,300
GRAND TOTAL