2016 PCC PATCHING PROJECT
PROJECT #216
PROJECT INFORMATION
The project will patch several areas of concrete streets around the City. This project is a needed maintenance project that has become possible through the additional funding received because of the increase in the State Fuel Tax. Funding for this project will come from the Road Use Tax Reserves.
FY 2017 ACTUAL
PRIOR YEARS
PROJECT
PRIOR YEARS
TOTAL
REVENUES
MISCELLANEOUS TRANSFERS IN
2,360.00
2,360.00
105,911.21
4,488.97
110,400.18
108,271.21
4,488.97
112,760.18
-
TOTAL REVENUES
EXPENDITURES CONSTRUCTION ENGINEERING
100,627.37
100,627.37 12,132.81
7,643.84
4,488.97
LEGAL FEES
- - -
MISCELLANEOUS TRANSFERS OUT
108,271.21
4,488.97
112,760.18
-
TOTAL EXPENDITURES
CAPITAL IMPROVEMENTS