4TH AVE W N DRAINAGE PROJECT
PROJECT #214
PROJECT INFORMATION
The project will correct drainage issues along 4th Ave W and W 18th Street that lie outside of any future project boundary. The City's funding for this project will come from the Storm Sewer Reserve fund.
FY 2017 ACTUAL
PRIOR YEARS
PROJECT
PRIOR YEARS
TOTAL
REVENUES
FEDERAL GRANTS MISCELLANEOUS
- -
TRANSFERS IN
567.00
4,721.88
5,288.88
-
TOTAL REVENUES
567.00
4,721.88
5,288.88
EXPENDITURES CONSTRUCTION ENGINEERING
-
4,721.88
4,721.88
LEGAL FEES
567.00
567.00
MISCELLANEOUS TRANSFERS OUT
- -
567.00
4,721.88
5,288.88
-
TOTAL EXPENDITURES
CAPITAL IMPROVEMENTS